ROAD WORK SCHEDULE: SUMMER 2025
ROAD SWEEPING: To be done April 24-April 29
ROAD GRADING: All roadwork listed is expected to be complete by the end of May
- Black Mountain Road: Grading
- Haskell Hill Road: Grading
- Lee Gray Road: Grading and gravel added
- Perry Hill Road: Grading
- Sam Ingalls Road: Grading and gravel added
- Wint Road: Grading
CULVERT CLEANING: Culverts will be inspected on Town owned roads starting the week of April 28. The clean out work will be contracted out after the scope of work is determined.
TRULL BROOK AND MARR ROADS: Repairs to the damaged sections of these roads will be conducted this summer, using FEMA disaster relief funds. Expect closures on the portions being repaired.
WEBBER POND ROAD: A project has been put out to bid to topcoat and preserve the portion of road reconstructed 2 years ago, with an option to repave the length of the road. A bid opening is scheduled for April 30, 2025 at 10:00am in the Town Office.
STATE ROADS: The State of Maine will be putting topcoat on the full length of the following roads this summer: Knights Hills Road, Lovell Road (93), Waterford Road, Bridgton Road (93).
ROADSIDE MOWING: Date TBD
- Town of Sweden Maine DOT Road List (February 6, 2018)
- Town of Sweden Maine Maine Public Bridge Structures Report (October 1, 2021)
- Maine DOT Work Plan for Calendar Years 2023-2024-2025 (March 27, 2023)
SAND & SALT
The Town of Sweden Sand and Salt shed is located on Hapsgood Road, just off Waterford Road and is ONLY to be accessed by the Road Commissioner and his winter road crews. Town residents may supply themselves with sand and salt for PERSONAL USE ONLY from the smaller building further along Hapsgood Road, on the right side of the road.