Installation of the box culvert is proceeding smoothly, with excellent progress being made. A dam had been installed to redirect water flow during construction, and the temporary bridge moved slightly downstream to allow passage. As of Aug 8, the bottom pre-cast and stone cover sections for the box culvert are in, tops are installed, and the dam had been removed.
![Temporary bridge relocated to allow passage while culvert is put in place](https://swedenmaine.org/wp-content/uploads/2023/08/haskell-6-768x1037.jpg)
![Looking towards where the box culvert will be set with temporary bridge moved further downstream](https://swedenmaine.org/wp-content/uploads/2023/08/haskell-8-768x1021.jpg)
![Box culvert sections awaiting installation](https://swedenmaine.org/wp-content/uploads/2023/08/haskell-9-768x1027.jpg)
![Box culvert sections awaiting installation](https://swedenmaine.org/wp-content/uploads/2023/08/haskell-7-768x977.jpg)
![Bottom pre-cast section of box culvert being installed](https://swedenmaine.org/wp-content/uploads/2023/08/haskell-4-768x986.jpg)
![haskell-1](https://swedenmaine.org/wp-content/uploads/2023/08/haskell-1-768x1024.jpg)
![Dam is out, bottom pre-cast sections and stone cover for box culvert are in place](https://swedenmaine.org/wp-content/uploads/2023/08/haskell-2-768x1030.jpg)
![Looking upstream from temporary bridge to newly set box culvert](https://swedenmaine.org/wp-content/uploads/2023/08/haskell-3-768x1067.jpg)