Installation of the box culvert is proceeding smoothly, with excellent progress being made. A dam had been installed to redirect water flow during construction, and the temporary bridge moved slightly downstream to allow passage. As of Aug 8, the bottom pre-cast and stone cover sections for the box culvert are in, tops are installed, and the dam had been removed.